McIntyre renovation update

Published: 18 January 2011

All the newÌýStrobicÌýchimneys have been installed on the McIntyre roof and are now working.

Seventy-five percent of theÌýnew HVAC system is now in operation. The remainder will be up and running by the end of February. Ventilation conduits are being installed in the mechanical rooms for exhaust as well as circulation.

The 8thÌýand 9thÌýfloor labsÌýare fully renovated (architecture, mechanical and electrical). New lab benches and exhaust hoodsÌýhave been installed. A portion of the 10thÌýfloor will be completed by the beginning of February.

Phase 1 of the new washroom construction has begun and washrooms on floors 1, 3, 5, 7, 8, 9, 10 and 13 are closed for renovation until Mid-February.

The tower crane will remain onsiteÌýuntil mid-February, in order to lift pipes to McIntyre's upper floorsÌýand close the façade.

Freezer farm installation (floorsÌý10, 11, 12 andÌý13) has begun and will be completed by Mid-February.