Construction Start: Bronfman Building - Computer lab 045-046

Rendering of new computer lab in Bronfman Building
Published: 14 December 2022

McGill University has mandated Corenov Constructeurs to carry outÌýthe following project: Bronfman Building / 18-094 - Computer lab 045 -046.

The project consists of transforming existing classrooms into two computer teaching labs with new audiovisual equipment and a reconfiguration. The scope includes the demolition of the back walls to include storage areas as part of the new teaching labs.

Project manager:ÌýJoé Normandeau (GPH Inc.) -Ìýjoe.normandeau [at] gph-inc.com

Assistant project manager:ÌýPierre Beauchamp (GPH Inc.) -ÌýPierre.beauchamp [at] gph-inc.com

Construction start date:ÌýJanuary 2023

Planned construction end date:ÌýAugust 2023

Work schedule: Monday to Friday, 7 a.m. to 10 p.m.

Scope of work:

There will be no exterior work related to this project. Interior work will affect the first basement, mainly around rooms 045 and 046, and will include some short interventions in the parking garage. Modifications to the existing electromechanical systems and fire protection are included. New audiovisual equipment and security accesses will be added.

±õ³¾±è²¹³¦³Ù:ÌýLimited access to rooms 043 and 047 during electromechanical work in the ceiling.