Construction Start: Strathcona Music Building - Building Envelope

±Ê³Ü²ú±ô¾±Ã©: 31 March 2023

McGill University has mandated Atwill-Morin to carry out the following project: Strathcona Music Building/ 16-135 - Envelope Renovation.

The project includes the reinforcement of the exterior walls supporting the roof structure, including interior works on the 5th ´Ú±ô´Ç´Ç°ùÌýand the renovation of masonry stones on the west façade. This is part of a project that spans multiple years addressing deferred maintenance repairs for the Strathcona Music Building, an over 125-year-old heritage building. In an effort to minimize disruptions to building users, the work is taking place during the summer months.

Project managers: André Labelle

Assistant project manager: Marcela Fernandez Pedrozo

Construction start date: May 2023

Planned construction end date: September 2023

Work schedule: Monday to Friday, 6 a.m. to 4 p.m.